IDGC of Centre, PJSC and IDGC of Centre and Volga Region, PJSC
(operating under the brands of Rosseti Centre and Rosseti Centre and
Volga Region) summed up the preliminary results of production
activities in 2019. In terms of a number of key indicators, the
companies exceeded the results of 2018.
The volume of boiler net supply of electricity for
the two Companies amounted to 93.3 billion kWh. The revenue from
electricity transmission activities, taking into account the volume
of services rendered in the territory where the companies perform the
functions of a supplier of last resort, is 185.5 billion rubles, its
growth compared to 2018 amounted to 4.9 billion rubles.
The work on connection to electric grids in 2019
was also summed up. According to the current data, in the reporting
period, the companies entered into more than 84 thousand grid
connection agreements, and more than 82 thousand contracts were
executed. The total connected capacity under the executed contracts
exceeded 1,700 MW, the total revenue from the grid connection
amounted to 2.6 billion rubles.
Last year, as part of the implementation of the
Environmental Safety Program aimed at implementing the Environmental
Policy of the electric grid complex, the companies performed 45
environmental protection measures in the regions of their activity.
84.5 million rubles were allocated for these purposes.
In turn, the results of the implementation of
measures to curb non-metered and non-contractual electricity
consumption for 2019 were summed up. In the course of large-scale
raid work carried out by personnel of Distribution Zones and
electricity metering departments of the companies’ branches,
including jointly with the security unit’s experts and law
enforcement agencies, 13,099 facts of illegal electricity consumption
were revealed in the regions of the service area of Rosseti Centre
and Rosseti Centre and Volga Region. The damage caused to the
companies amounted to 919.02 million rubles. The power engineers took
measures to compensate for the damage caused to the companies. On the
facts of the illegal electricity consumption law enforcement agencies
initiated 22 criminal and 4,325 administrative cases, 5 people were
brought to criminal proceedings, 1,931 people to administrative
responsibility. Two were convicted by a court verdict. The energy
companies reimbursed 478.4 million rubles.
In 2019, the companies continued their systematic
work to reduce receivables for electricity transmission services. One
of its most effective areas is the claim-related activity. According
to the recent data, at the end of 2019, the volume of claims of the
companies satisfied by the courts amounted to 4.6 billion rubles, of
which 3.5 billion rubles were claims on electricity suppliers of last
resort in the regions. According to the decisions on the collection
of overdue debts, 0.4 billion rubles were repaid (50% of the total
amount that appears on the writ of execution). As of 1 January 2020,
the total amount of receivables of Rosseti Centre and Rosseti Centre
and Volga Region for electricity transmission services was 47.1
billion rubles, including 32.3 billion rubles in arrears, of which
29.1 billion rubles - overdue debts of the suppliers of last resort.
The companies intend to consistently continue the work on their
recovery. So, as of 1 January 2020, 1,240 cases were pending before
the courts of various instances, initiated by the legal unit of
Rosseti Centre and Rosseti Centre and Volga Region to collect debts
in aggregate of 38.2 billion rubles, including 756 cases totalling
claims of 37.4 billion rubles regarding the suppliers of last resort.
The implementation of the production programs of
Rosseti Centre and Rosseti Centre and Volga Region made it possible
to ensure the quality and reliability of power supply to consumers in
20 constituent entities of the Russian Federation, and significantly
contributed to uninterrupted and stable operation of the electric
grid complex of the companies in these regions throughout the year.
Other IR-news can be found on
the website.
|